A century of infrastructure is wearing out
We estimate what the world built in a hundred years, how much has worn out, and how Jordan and Aqaba can plan the renewal as PPPs.
For a hundred years the world built roads, pipes, power lines, ports and dams one piece at a time, and by our estimate that century of work was worth about $140 trillion in 2025 dollars. About $60 trillion of it has already worn out or been retired, and much of what remains is now ageing together.
How much infrastructure has the world built in the last 100 years?
By our estimate, the world built about $140 trillion of infrastructure over the hundred years from 1926 to 2025, measured in 2025 dollars. That covers roads, rail, ports, airports, power, water and telecommunications. The figure rests on one stated assumption, and leaders in Jordan and Aqaba can check it in three steps.
- 01Add up a century of income. World Bank figures for 1960 to 2025, and the Maddison Project Database 2023 of the University of Groningen for the years before 1960, put everything the world produced from 1926 to 2025 at about $3,750 trillion in 2025 dollars.
- 02Find the share spent on infrastructure. A 2013 study by the McKinsey Global Institute found that the world has spent about 3.8% of its income on roads, rail, ports, airports, power, water and telecommunications, based on 84 countries from 1992 to 2011.
- 03Apply that share to the whole century. If the world spent the same 3.8 cents of every dollar in every year from 1926 to 2025, it built about $140 trillion of infrastructure.
The result is an estimate built on that one assumption. If the real share was higher in some decades and lower in others, the total moves with it, so the figure gives the scale of the century’s work rather than an exact count.
$140T
of infrastructure built by the world from 1926 to 2025, in 2025 dollars, by our estimate from World Bank, Maddison Project and McKinsey Global Institute figures
How much of the world’s infrastructure has already worn out?
About $60 trillion of the infrastructure the world built over the century has already worn out or been retired, and about $80 trillion still stands. For public bodies, utilities and banks in Jordan and Aqaba, the gap shows how much of any infrastructure plan goes to replacing what earlier generations built.
The calculation takes two more steps. The same 2013 study by the McKinsey Global Institute found that the infrastructure a country has standing is worth around 70% of its yearly income. World Bank figures put the world’s income in 2025 at about $118 trillion, so the infrastructure standing today is worth about $80 trillion. Take that from the $140 trillion built and about $60 trillion is left over, the value that wore out or was retired as roads, pipes, plants and lines reached the end of their lives.
$60T
of the century’s infrastructure already worn out or retired, the gap between about $140 trillion built and about $80 trillion standing in 2025
Renewal is already a large part of the bill. The same study found that renewing ageing infrastructure takes about 40% of all infrastructure investment, with the rest going to expansion.
Why is the world’s infrastructure wearing out?
Infrastructure wears out because every road, pipe, power line and dam is built for a working life, and much of the world’s stock is reaching the end of the life it was designed for. Dams are the clearest example, and the same logic applies to the pipes, reservoirs and pumping stations that Jordan’s water guides prepare as PPPs.
A 2021 report from the United Nations University, “Ageing Water Infrastructure: An Emerging Global Risk”, found that most of the world’s 58,700 large dams were built between 1930 and 1970 with a design life of 50 to 100 years. By 2050, the report found, most people on Earth will live downstream of large dams built in the 20th century, many of them already at or beyond their design life.
Inside a network, wearing out starts small and out of sight. The Jordan PPP guides for water and network companies describe robots that travel inside pipes to find leaks and weak sections, and the world’s biggest computer pictures a pipe in Amman that notices a small leak and reports it before anyone sees a puddle.
Why is so much infrastructure coming due at the same time?
By 2075, everything the world built over the century will be at least fifty years old. About $22 trillion of the total, built between 1926 and 1975, is already past fifty, and a far larger wave built since 2000 reaches fifty between 2050 and 2075. Planners in Jordan and Aqaba work inside that same window.
The large dams built between 1930 and 1970 belong to the first wave. The second wave is the boom since 2000: more than half of the century’s total, about $84 trillion, was built between 2000 and 2025. Those assets are young today, and their renewal will arrive on top of the work on everything older.
What will it cost to rebuild the world’s infrastructure?
Rebuilding and running the world’s infrastructure will take about $500 trillion over the next fifty years: $300 trillion to build, $150 trillion to operate and maintain, and $50 trillion for the sensors, compute and robotics inside the assets. Jordan’s $86 billion of PPP and infrastructure projects, $46 billion of them anchored in Aqaba, are part of that rebuild.
$300T
to build infrastructure over the next fifty years, more than twice the whole of the last century’s $140 trillion
The last century was built without a plan as one system. The world’s biggest computer calls it the largest thing people have ever built, a machine that grew over the last hundred years one road and one pipe at a time. The next fifty years can be built and run as one machine. EarthOS is the shared AI software that would run it.
Three technologies carry that change. Artificial intelligence designs and runs the assets, robotics builds and maintains them, and tokenization finances them and opens their ownership to everyone. Together they point towards the infrastructure singularity.
Every new pipe, road and power line can be laid with sensors inside, because adding them on the day it is built costs little and adding them later costs a great deal.
That makes renewal the cheapest moment to add intelligence, because each pipe, substation and stretch of track renewed in the coming decades can join the machine on the day the work is done.
What does ageing infrastructure mean for Jordan and Aqaba?
In Jordan and Aqaba, the Jordan PPP guides treat renewal as PPP work. Jordan still loses about 41% of its water to leaks, theft and faulty meters, and the water and network guides prepare pipe replacement, reservoirs, pumping stations and substations as PPPs, each with a partner that finances the upgrade and is paid from the savings it delivers.
Machines make that work measurable. Robots travel inside pipes to find leaks and weak sections, drones survey transmission lines, reservoirs and track, and crawlers inspect substations and pumping stations, so every inspection is recorded as data. The water sector guide records non-revenue water at 41% nationwide in August 2026, against a 2040 target of 25%.

Renewal reaches transport as well. The transport sector guide lists the Amman-Zarqa Light Rail, a 60 km line that would rehabilitate the old Hejaz Railway between Amman and Zarqa and extend it to Queen Alia International Airport. The project is proposed for private construction and operation.
Jordan has about $86 billion of PPP and infrastructure projects in development, $46 billion of them anchored in Aqaba, and many of them will connect to the water, power and rail networks that state-owned companies run. Each new connection needs the network behind it to keep pace, so new building and renewal belong in the same plan.
What can an organization in Jordan do about ageing infrastructure now?
An organization in Jordan or Aqaba can launch a PPP program of its own that plans renewal beside new building. The guides describe the pieces: a small PPP unit, performance-based contracts, a research lab that runs small PPPs in parallel, an open door to direct proposals, and upgrades prepared for AI, robotics and tokenization.
Small PPPs let a utility test leak reduction in one district, a battery at one substation or smart meters on one street, and measure each result from the first day before it commits to a large upgrade. PPP Regulation No. 9 of 2024 defines small-scale PPPs below $14.1 million, which can be bundled into one feasibility report and one tender.
Unsolicited proposals open a second door. Article 15 of PPP Law No. 19 of 2023, which took effect on November 13, 2023, lets a company take its own PPP idea to the Ministry of Investment or a public authority. A water company that sees where a network loses water can propose leak reduction in one district and keep the right to match the best offer if the project goes to tender.
The guides for water companiesDownload the guide, state-owned utilitiesDownload the guide, municipalitiesDownload the guide and transport companiesDownload the guide set out each program step by step, and the opportunity page shows the rebuild at world scale. The century behind us built about $140 trillion without a plan for the whole, and the organizations in Jordan and Aqaba that plan renewal and new building together will shape the next.