Sync or sink

Every PPP has two halves, and Jordan’s $86 billion of projects will move only as fast as the public and private sides move together.

By Saad I. Sahawneh

Share

A PPP works when the public and private sectors move in step: government prepares and tenders projects on a clear timetable, and companies have teams ready to bid, finance, build and run them. When the two drift apart, projects sink into delay, and Jordan’s $86 billion of projects can only move as fast as both sides move together.

What does it mean for PPP partners to be in sync?

In Jordan, being in sync means the public body and the private company work to the same plan, the same timetable and the same rules. Government knows what it wants to buy and when. Companies know what is coming and have a team ready before the tender opens, so neither side waits for the other.

A PPP is one contract with two halves. A ministry or public authority sets the service it needs and pays for it or lets users pay. A private partner designs, finances, builds and runs the asset. The PPP starting guide explains the models, and every one of them depends on both halves moving at the same time.

Why do PPPs sink when the two sides drift apart?

PPPs in Jordan sink when one side is ready and the other is not. A ministry that tenders without a team to supervise the contract slows every step. A company that waits for the tender before building its team arrives late, prices the risk high and often stays out of the bidding altogether.

The cost shows up as lost time. Studies sit on shelves, tenders are repeated and investors move their money to markets that answer faster. The old way of working puts years of study in front of one large project, and a country that spends its money studying one big project gets one answer, years later.

The World Bank counted 315 private infrastructure projects reaching financial close across all low and middle income countries in 2024, only a few per country. A country where government and companies move together can close far more than its share.

How has Jordan kept PPPs in sync before?

Jordan has built with PPPs for more than 20 years, and its best projects show both sides moving together. The As-Samra wastewater plant reached financial close in 2003, Airport International Group signed a 25-year concession for Queen Alia International Airport in 2007, and Amman East, the country’s first independent power plant, opened in 2009.

The National Water Carrier shows the same rhythm at a much larger scale. A group led by Meridiam and Suez signed the BOT contract on January 12, 2025, and the final agreement followed on April 21, 2026, at about $4.3 billion to build. It will carry 300 million cubic meters of Red Sea water a year from Aqaba to Amman, with water due to flow from 2030.

The laws kept pace too. PPP Law No. 19 of 2023 took effect on November 13, 2023, PPP Regulation No. 9 of 2024 followed, and the PPP Unit now sits at the Ministry of Investment.

Stained-glass illustration of a port with ships and tall industrial towers seen through a blue glass arch at sunset, with open sea on the left.
In Aqaba, the port, the zones and the National Water Carrier already bring public bodies and private partners to the same table.

What does the public sector need to do to stay in sync?

Jordan’s ministries and public authorities stay in sync by running PPPs as a program instead of a string of one-off deals. A program gives each body a small team, a list of projects that can go to market one after another and standard contracts that companies already understand. The ministries guideDownload the guide sets out how.

  1. 01A PPP team: a small dedicated team follows each project from the first market sounding to the end of the concession.
  2. 02A published project list: companies see what is coming and prepare years ahead.
  3. 03Standard contracts: similar projects use the same documents and can be bundled into one tender.
  4. 04One route for direct proposals: Article 15 of PPP Law No. 19 of 2023 lets any company bring its own unsolicited PPP proposal, and a fast track gives every ministry the same route and the same timetable.
  5. 05Small pilots in parallel: 1% of the budgets of Jordan’s 40 contracting authorities, about $78 million, would fund 780 small PPPs a year.
A government that prepares, tenders and supervises its PPPs as one program can set a model the region can follow, with each ministry’s results open to the others.

How can the Royal Hashemite Court, the Prime Ministry and the ministries stay in sync?

Being in sync starts inside government. Many PPPs cross several ministries at once: a water line needs power, land and a road beside it, and a port needs transport, energy and customs. The Royal Hashemite CourtDownload the guide, the Prime MinistryDownload the guide and the ministries and public authoritiesDownload the guide move fastest when they work from one plan and read the same numbers at the same moment.

  1. 01The Royal Hashemite Court: champions the national priorities across every sector and can follow them in live numbers, from water saved to power lost on the line.
  2. 02The Prime Ministry: coordinates the ministries, sets shared rules for data and keeps one view of what every project delivers, so a decision that touches water, energy and roads is taken once, together.
  3. 03The ministries and public authorities: each keeps its own projects and data, adds them to the shared picture and sees what the others see before it plans, builds or spends.

Much of that picture already exists in the sensors Jordan runs today. The Ministry of Water and Irrigation and the water companies read water meters, and the National Water Carrier will watch its whole pipeline for leaks with fiber optic sensing. Smart meter installation for electricity reached 96% by the end of 2025. The Ministry of Energy and Mineral Resources runs 23 seismic stations, the Ministry of Environment runs 27 air quality stations, and the Greater Amman Municipality watches the capital’s roads with about 5,600 cameras. The sensors page explains what each kind of sensor measures.

When those readings flow into one shared picture, a heatwave shows up in power demand, water use and air quality on the same afternoon, and the ministries for energy, water and the environment act on it together. A street is opened once for water pipes, fiber and power cables, because every owner sees the plan before the first trench. It starts with shared rules for how project data is named, stored and protected, and a line in every new PPP contract that sends its data to the shared picture from the first day.

What does the private sector need to do to stay in sync?

Companies in Jordan stay in sync by building their PPP capacity before the tenders arrive. Banks, contractors, developers, operators and technology firms each need a small PPP team that knows how projects are prepared, procured and financed, and that follows Jordan’s pipeline from the first market sounding.

That team turns a company from a bystander into a partner. It can answer a market sounding with real numbers, join a consortium early, bring a direct proposal under Article 15 and price risk fairly because it understands the contract. The guides for PPP developersDownload the guide, contractorsDownload the guide and banksDownload the guide show how each one can launch its own PPP program.

When both sides have a team, they speak the same language. The ministry hears early what the market can deliver and at what price, and the company hears early what the ministry needs, so the tender that follows is one both sides are ready for.

Where can Jordan and Aqaba start?

Jordan has $86 billion of PPP and infrastructure projects in development, with $46 billion of them anchored in Aqaba. They are spread across many ministries and public authorities, and they will move fastest when those institutions and their private partners work from one approach and learn from each other’s results.

$86B

of PPP and infrastructure projects in Jordan, with $46 billion anchored in Aqaba

Aqaba is the natural place to show it. It is small enough to test a new idea quickly and busy enough to prove it, and the Aqaba guideDownload the guide shows how an organization there can launch its own PPP program.

The first step is the same on both sides: name a small PPP team, study the project list and meet the other side early. The opportunity page shows where the $86 billion sits, so government and companies can start from the same map.