Every PPP model explained
What each type of PPP model means, how the private partner is paid, and the project in Jordan that shows it at work.
The main types of PPP model are BOT (build, operate, transfer), BOO (build, own, operate), BOOT (build, own, operate, transfer), DBFO and DBFOM (design, build, finance, operate, maintain), DBFM (design, build, finance, maintain), the concession, the management contract and the availability payment PPP. Each one sets who designs, builds, finances, runs and owns a public asset, for how long, and who pays the private partner. Jordan has a working or planned project for every one, from the As-Samra wastewater plant to the passenger railway proposed between Amman and Aqaba.
What are the main types of PPP?
A PPP model is the deal behind a project. The contract decides who designs, builds, finances, operates and owns the asset, for how long, and how the private partner is paid, by users through fees or by the government through availability payments. Each of the main models has a project in Jordan to learn from.
What is a PPP? explains the idea itself. The models are the different ways of writing the contract:
- 01BOT: the partner designs and builds, operates for a fixed term, and hands the asset back; paid by users or the government; Jordan example: As-Samra wastewater plant.
- 02BOO: the partner builds, owns and operates, with no handback; paid by users or a state buyer; Jordan example: the Mafraq wind farm.
- 03BOOT: the partner builds, owns and operates for a fixed term, then transfers the asset; paid by users or the government; Jordan example: Al Mujib pumped-storage dam.
- 04DBFO and DBFOM: the partner designs, builds, finances and operates, and in a DBFOM maintains the asset too; paid by users or the government; Jordan example: Amman Bridge.
- 05DBFM: the partner designs, builds, finances and maintains, and the government runs the service inside; paid by the government; used for schools, hospitals, courts and railway track.
- 06Concession: the partner takes over an existing service and invests in it; paid by its users; Jordan example: Queen Alia International Airport.
- 07Management contract: the partner runs a service for a fee and the public side keeps the assets; paid by the public owner; Jordan example: Yarmouk Water Company.
- 08Availability payment PPP: the partner keeps an asset open to the agreed standard; paid by the government; Jordan example: Madaba Government Hospital.
What is the difference between BOT, BOO and BOOT?
The difference is who owns the asset at the end. In a BOT the partner builds and runs the asset, then hands it back after a fixed term. In a BOO the partner keeps it. In a BOOT the partner owns it during the term and transfers it at the end. Jordan has projects under all three.
BOT is the classic model. The partner raises the money, builds the asset, runs it for 20 to 30 years and hands it back in good working order. The As-Samra wastewater plant, Jordan’s first major build-operate-transfer project, treats about 70% of the country’s wastewater for Amman and Zarqa under a concession that ends in 2037.
The Aqaba to Amman Water Desalination and Conveyance project, led by Meridiam and Suez, is a build-operate-transfer project too, and a build-operate-transfer model is under consideration for the passenger railway between Amman and Aqaba.
$5.8B
build-operate-transfer project to desalinate Red Sea water at Aqaba and supply about 40% of the kingdom’s drinking water
In a BOO (build, own, operate) the partner keeps the asset for its whole life. Power plants often use it. Jordan is offering a 200 MW solar program and a 100 MW wind farm in Mafraq on a build-own-operate basis, with the wind farm selling its power to NEPCO.
A BOOT (build, own, operate, transfer) sits between the two, because the partner owns the asset during the contract and transfers it at the end. On October 15, 2026, Jordan’s Ministry of Investment opened prequalification for the 450 MW Al Mujib Pumped-Storage Hydropower Dam as a BOOT PPP, with applications due January 18, 2027.
What does DBFO mean?
DBFO means design, build, finance, operate. The private partner designs the asset, builds it, raises the money and runs it, and a DBFOM adds long-term maintenance. Jordan is offering the Amman Bridge, a 15.8 km elevated toll expressway along King Abdullah II Road, as a design, build, finance, operate and maintain PPP.
One team is then accountable for the design, the build and the asset’s performance over decades, and the model is common for roads, hospitals and schools.
Projects add or drop a letter to fit the need. The Aqaba-Ma’an Dry Port is planned as a design, build, finance, operate and transfer project, and the Abu Al-Zighan desalination upgrade is a design, build and operate contract financed by the EIB. Dropping the O gives DBFM.
What is DBFM?
DBFM means design, build, finance, maintain, and it leaves out operate. The private partner designs the building, builds it, raises the money and keeps it in good working order for 20 to 30 years, while the government runs the service inside. Teachers, doctors and judges stay public employees, and the partner looks after the roof, the lifts, the air conditioning and every system that keeps the building working.
The government pays through availability payments, which start when the building opens and drop when a classroom, ward or courtroom falls short of the agreed standard. Schools, hospitals, universities and courts often use the model, and the rail companies guideDownload the guide applies it to new track and signaling, paid for keeping each section open at its rated speed and axle load.
Why do investors choose DBFM?
Investors choose DBFM because it gives them risks they can control and steady income for decades. Four reasons stand out:
- 01Risks they can manage: the partner carries the design, the build and the condition of the building, which are engineering risks it can price. The service inside, with its staff, its users and its results, stays with the government.
- 02Steady income: the fee depends on the building being open and up to standard, so patient numbers and class sizes leave it unchanged. That income matches long-term debt and suits pension funds and insurers.
- 03Cheaper money: lower risk lets lenders lend more at lower rates, so the partner can bid a lower payment and still earn its return.
- 04Whole-life design: the team that designs the building also pays to maintain it for decades, so it picks materials and systems that cost less over the life of the asset.
Governments gain from the same split. A ministry keeps its staff and its policies, gets the building on time because payment starts only when it opens, and protects its upkeep from budget cuts for the length of the contract. The Madaba Government Hospital shows the split in Jordan: under a build-lease-transfer deal signed in July 2025, KBW Investments builds the 260-bed hospital and the Ministry of Health equips and runs it.

What is a concession?
A concession gives a private partner the right to run a public service for a fixed term and charge its users. The partner invests in the service and collects the fees. In Jordan, Queen Alia International Airport has been a build-operate-transfer concession since 2007, and in February 2025 the government and the operator confirmed its extension to 2039.
A management contract is a lighter form. The partner runs a public service for a fee, while the public side keeps the assets. In May 2026 Veolia took over operation, maintenance, billing and customer service for the Yarmouk Water Company under a four-year contract, renewable for two more, with payment tied to service, efficiency and revenue results.
What is an availability payment PPP?
In an availability payment PPP the government pays the partner a regular fee for keeping an asset open and in good working order, instead of users paying fees. Payments drop when the asset falls short of the agreed standard. In Jordan, the Madaba Government Hospital is paid in installments over ten years after completion.
The model suits schools, hospitals and roads without tolls, where people use the asset without paying the partner. The partner carries the risk of keeping it working. The facility management guideDownload the guide shows the deductions at work: a ward, classroom or platform that falls below the agreed standard lowers the payment.
Availability payments run for decades. The parliament guideDownload the guide asks for clear reporting on each one, so Parliament can approve the budgets that pay for PPPs with a full view of their risks.
How do you choose the right PPP model?
The right PPP model depends on four questions: who is best placed to carry each risk, whether users can pay fees, whether the asset already exists, and how large the project is. In Jordan the answers point a toll road to DBFOM, a power plant to BOO and a running utility to a management contract.
A PPP moves each risk to the party best able to manage it.
Risk comes first. Sponsors carry the equity and contractorsDownload the guide carry the build. Infrastructure fundsDownload the guide carry the first loss, and law firmsDownload the guide negotiate the documents that decide who carries each risk for the life of the project.
Fees and the asset come next. A toll road, an airport or a power plant can earn from users or a state buyer, so BOT, BOO and concessions fit. A school earns nothing from users, so a DBFM paid through availability payments does the work. A service already running, such as a water utility, suits a concession or a management contract.
Size shapes the rest. A PPP takes about seven years and roughly 10% of its capital cost to reach financial close, according to the PPP developers guideDownload the guide. Small-scale PPPs below $14.1 million can be bundled into one feasibility report and one tender. The PPP pyramid sets out the sizes, and the small PPPs page explains the method.
Which PPP models does Jordan use?
Jordan uses BOT for water, BOO for new solar and wind, BOOT for pumped storage, DBFOM for its first elevated toll road and a concession for its main airport. New projects follow PPP Law No. 19 of 2023, which took effect on November 13, 2023, and its Article 15 lets any private company propose its own project.
Jordan’s 2023 PPP law explained covers the rules. A direct proposal under Article 15 lets an organization propose the model that fits its own idea, from a small concession to a full BOT, and the unsolicited proposals page explains the route.
$86B
of PPP and infrastructure projects in development in Jordan, $46 billion of them anchored in Aqaba
Jordan’s $86 billion pipeline is the place to see every model at work, and Aqaba anchors $46 billion of it, around the zone and the port. The wastewater and solar sector guides list the projects behind As-Samra and Mafraq, and the summary of all 96 guides shows every kind of organization how to take part.