Unsolicited PPP proposals in Jordan
Article 15 of PPP Law No. 19 of 2023 gives every company in Jordan a direct route to government, and PPP Regulation No. 9 of 2024 sets out each step from submission to tender.
An unsolicited PPP proposal in Jordan is a project idea that a private company brings to government on its own initiative, under Article 15 of PPP Law No. 19 of 2023. The company submits it to the Ministry of Investment, which has 60 days to study it or return it unopened, and a listed project then goes to a competitive tender where the proposer can match the best offer. This post follows each step, from the first submission to the tender, for companies in Jordan and Aqaba.
What is an unsolicited PPP proposal in Jordan?
An unsolicited proposal, also called a direct proposal, is a PPP idea that a company in Jordan prepares and brings to government before the government asks for it. Article 15 of PPP Law No. 19 of 2023 lets any private company submit one, and Articles 53 to 58 of PPP Regulation No. 9 of 2024 set the rules.
The route suits companies that already know where a public service falls short. A logistics company sees where cargo waits and where storage is missing, a mining company knows where the rail, port, water and power around its sites fall short, and a contractor can bring a project it has already costed and planned. Each can turn that knowledge into a project of its own design. The unsolicited proposals page sets out the full route, with links to both laws.
What conditions must an unsolicited proposal meet in Jordan?
Article 53 of PPP Regulation No. 9 of 2024 sets six conditions for every direct proposal in Jordan. The proposal must bring an innovative way to deliver or improve a public service, come from the company’s own initiative, deliver value for money, and earn project revenues that equal or exceed the government’s obligations.
- 01Innovation: an innovative way to deliver or improve a public service.
- 02Independence: prepared by the company on its own initiative, without a request, involvement or guidance from any government body.
- 03Value for money: the project must deliver value for money.
- 04Revenues: the project’s revenues equal or exceed the government’s obligations.
- 05Fit: the idea fits the government’s development programs and the public authority’s priorities.
- 06Disclosure: the company discloses any conflict of interest and any link to the officials, committees, advisers and their relatives involved.
The revenue condition favors projects that earn their own way, from user payments, savings or other income, because the project’s revenues must at least match what the government commits to it. The independence condition keeps the route for ideas that start outside government: a proposal prepared at the request of a government body, or with its involvement, guidance or supervision, falls outside Article 53.
What goes into an unsolicited proposal in Jordan?
Under Article 54, a direct proposal in Jordan must carry at least six things: the scope and a description of the project, the company’s profile and experience, a preliminary feasibility study with the details of the innovation, the fiscal impact on government, a grant of rights to the intellectual property, and the cost of the studies with proof.
Two of these items protect each side. The company names any intellectual property and trade secrets behind the idea, and grants the government the right to use them if the project is tendered. It also declares what its studies cost, with proof. The government is under no obligation to repay that cost, and the declared amount later caps what the proposer can recover at tender. The Ministry can also charge a fee to receive a proposal.
The guide for law firmsDownload the guide calls direct proposals legal work from the first page, from the conditions and the intellectual property to the conflict-of-interest disclosure. The guide for banksDownload the guide adds the other half: every direct proposal needs a financial case and a lender willing to stand behind it.
How does the Ministry of Investment review a proposal?
In Jordan, a direct proposal goes to the Ministry of Investment, and a proposal sent to any other public authority is passed on to the Ministry. Within 60 days of receiving it, the Ministry decides whether to study the proposal or return it unopened, and while it studies it, the Ministry can ask for more information.
60
days for the Ministry of Investment to study a direct proposal or return it to the company unopened
The Ministry can charge a study fee, set by its PPP Unit, of at least JD 5,000. When the study is done, Article 57 leaves the Ministry two decisions: it lists the project in the national registry of public investment projects, or it rejects the proposal and tells the company.
What happens to a proposal after it is listed in Jordan?
A listed proposal in Jordan follows the PPP law like any other project: a feasibility report, approval by the High Committee for PPP Projects, a competitive tender and award by the Cabinet. The tender tests the idea against the market, and Article 58 gives the proposer two rights that the tender documents must state.
The first is a right to match. If the proposer’s offer matches the best technical and financial offer, the proposer wins. The second covers its early work. If another bidder wins, the proposer’s direct study costs are repaid, up to the amount it declared and as the Ministry decides, and the winning bidder pays them.
How can companies in Aqaba use unsolicited proposals?
Aqaba holds $46 billion of Jordan’s $86 billion of PPP and infrastructure projects, and the companies working there see where its port, zones and corridors need new services. Article 15 gives each of them the same direct route to government as any company in Amman, with the same right to match at tender.
$46B
of Jordan’s $86 billion of PPP and infrastructure projects are anchored in Aqaba
A direct proposal lets an organization in Aqaba bring a project built around a need it knows better than anyone, from a cold store at the port to a service on the coast.
The sector guides already list ideas to start from. The logistics sector guide suggests a digital port community system for Aqaba, the mining sector guide a rail siding or bulk storage yard on the corridor to Aqaba, and the guide for economic zone and industrial city developersDownload the guide shows how a manufacturer, a logistics company or a utility partner in a zone can bring its own idea forward under Article 15.

Where should a company in Jordan start with a direct proposal?
A company in Jordan can start with the steps on the unsolicited proposals page, which links PPP Law No. 19 of 2023 and PPP Regulation No. 9 of 2024, and with the guide written for its own kind of organization. Every organization guide has a section on direct proposals, and every sector guide lists projects to start from.